Monday, January 30, 2012

Drywall

The drywall and fire ceilings are being installed throughout the administration area. The shop and storage areas walls will be constructed out of plywood. All of the electric and plumbing is mostly complete throughout the adminstration section.

Friday, January 13, 2012

Snow

Well our first snowfall of the year was not a huge amount. We received about an inch yesterday before it changed over to rain. What ever snow remains will be here for at least a little while due to the frigid temps over the weekend.

Wednesday, January 11, 2012

Material Storage Bins

The material or bulk storage bins were located this week. The blocks pictured to the left will make up the walls on the outside and insides of each bay. The base will be a concrete pad which we are hoping to pour next week. This bins will allow us to store topdressing, mulch, and gravel in large volumes on site.

Monday, January 9, 2012

2nd Deck

This is a view from inside the 2nd level of equipment storage. The floor is the last component to be finished along with utilities. The floor will be comprised of 3.5 inches of concrete. Once the heat is installed throughout the building; the contractor will pour the floor.