Tuesday, September 27, 2011

Construction Update

The foundation for the GMC building (left) is being constructed and should be completed by next week. The EMC building interior walls are being erected and the exterior block will begin toward the end of the week. We are hopeful to have the floor poured (weather permitting) sometime late next week.

Monday, September 26, 2011

Topdressing

Fairway topdressing continues today and should be wrapped up this week. The last few fairways remaining are completed and the staff is going over the wetter, low-lying fairways again. The sand has incorporated nicely into the turf canopy.

Friday, September 23, 2011

EMC Foundation

The foundation for the EMC building has been back filled. The next step in installing the interior masonry block located in the upper right of the photo. The block will be installed next week.

Thursday, September 22, 2011

Thanksgiving already?

One of our many species of wildlife on the course....turkeys. There favorite spots to hang-out are usually on the 3rd and 4th holes. As a Virginia Tech graduate, these guys always make me smile.

Monday, September 19, 2011

Fairway Topdressing

Fairways are being aerated and topdressed this week. Below is our new fairway topdressor on the 2nd fairway. The goal is to put down close to 20 tons / Acre of sand on the fairways. This process will improve drainage, firm up the surface, and help reduce those pesky earthworms. I am hopeful with good weather to be completed this week.

Friday, September 16, 2011

1st Cut

Greens were cut for the first time since aeration. The holes are closing nicely and with a few more days of warm weather; they should be healed in shortly. The process of mowing involves using are older, duller mowers until the sand is worked in enough to allow for the regular greens mowers.

Fescue

Much of the fescue throughout the course has been cut back for the fall. This gives us an opportunity to treat these areas as needed for weeds and unwanted grasses. It also makes leaf and debris cleanup easier in the fall and spring.

Thursday, September 15, 2011

Aerification

Greens and approaches have been aerified and topdressed this week. I am hopeful with good weather, proper water and fertility, the hole shsould close in a few weeks. We have begun the process of aerifying the tees; with completion early next week. Fairway aerification will begin on Monday and should take a few days to complete. The fairways will be topdressed this season.

Monday, September 12, 2011

Grounds Management Center

Construction is moving along for the new Grounds Management Center (GMC). Foundations for the Environmental Center has been poured and the GMC scheduled to be completed next week.