Wednesday, December 21, 2011
Saturday, December 10, 2011
GMC Floor
On Friday, the floor or slab for the GMC building was poured. The crews worked all day and into the evening to get the slab poured and leveled out. An estimated 14 concrete truck loads was needed. The floor takes a few days to set up before framing can begin.
Wednesday, December 7, 2011
Temporary Greens
The course is switching over to temporary greens for the season with forecasted cold weather and possible snow on the horizon. The greens will be roped off for the season and we will be installing covers on several greens this winter. The covers aid in protection from the winter elements. All of our topdressing and plant protectants were completed last week.2nd Level
Tuesday, December 6, 2011
More Drainage
Monday, December 5, 2011
Electrical Conduit
Tuesday, November 29, 2011
Coming Together
The roof over the administration building is completed and the sheeting along the sides has started. There are many subs on site including plumbers, electricians, masons, site and steel workers. The construction site is a busy place! Progress is moving along nicely with the entire site close to finish grade.Monday, November 21, 2011
Irrigation Blowout
The irrigation system is being blown-out this week. The process usually takes about two days to complete. This is accomplished with an air compressor hooked up to the irrigation system pumping in a large volume of air. The goal is to remove most of the water in the lines so any remaining water has room to expand. A good job now means less headaches in the spring time.Saturday, November 19, 2011
Wednesday, November 9, 2011
EMC Roof Installation
Saturday, November 5, 2011
Taking Shape
Friday, October 28, 2011
Frost
are similar to egg shells when frost occurs and can break apart from the slightest pressure. Although not instantly apparent within 1 to 2 days the plant leaves will turn black and leave an unsightly footprint or tire track.
Tuesday, October 25, 2011
Water Main
The water main is being installed through the member's parking lot. The picture shows the new line (black) traveling through the lot under the electric lines. The water main has to be installed below the frost line around 5 feet in depth. The site contractor should be to the new building by week's end.Monday, October 24, 2011
GMC Building Update
Friday, October 21, 2011
Fuel Tank Arrives
Thursday, October 20, 2011
Foundation
Wednesday, October 19, 2011
Building Arrives
Monday, October 17, 2011
Utility Installation
The water and gas main lines are beginning installed this week. The trench will begin near the island in the center of the clubhouse parking lot and travel through the main parking lot. The trench will be done in stages to allow access to the clubhouse and lots. Hopefully, the trench should be completed by week's end.