Saturday, March 31, 2012

Moving Day

With the maintenance building nearing completion we were able to start our move today. All the members of the grounds staff pitched in with moving equipment and materials, assembling shelves and organizing rooms. A good deal of equipment was moved today and we are planning on moving the remainder over the next week or two.

Tuesday, March 27, 2012

Hydroseeding at GMC Building

Areas around our new maintenance building were hydro seeded today. A native blend of fescue grasses was applied to the hillsides as shown in the picture. The grass plants will help stabilize the banks. The landscaping around the buildings will be completed in the next few weeks.

Monday, March 19, 2012

Cutting greens

Today we cut greens for the first time in 2012. The course will open on Wednesday at 12pm for the 2012 season. If winter should return over the next few weeks; the course will be closed for a few days until conditions can improve. Looking forward to seeing everyone on the course in the next few months!

Monday, March 12, 2012

Covers Removed Today

With the forecast in concord to hit 70 degrees; the staff removed all the covers from the greens and tees. The turf underneath looks great and will have a nice head start in the spring. If the colder temps return, we will put the covers back on in the evenings for an extra layer of protection.

Stump Grinding

The tree removal along the front entrance has been completed. Today the stump grinding began on the larger sugar maples. The grindings will be removed and the holes will be filled in with soil and seeded. The stumps located in the planting beds will be mulched in preparation for new plantings this spring.

Thursday, March 8, 2012

ABW (Hyperodes) Traps

Today we installed five pitfall traps around the course. These traps are designed to track annual bluegrass weevils that are moving from the treeline/roughs towards the fine turf areas. By counting the adults captured it will give the staff an advantage and an idea of populations for this upcoming year. Pitfall traps are an integral part of Integrated Pest Management Program and will help us prepare for any necessary course of action.


Wednesday, March 7, 2012

Front Entrance Tree Work Continued

.
.
.
.
.
.
.
.
.
.
The tree work along the front entrance was continued today. Several smaller trees near the entrance house and along the paddle ball courts were removed. Many of these trees were locust trees; an invasive species in this area. The remainder of the tree work will be completed by Friday.

Tuesday, March 6, 2012

Front Entrance Tree Work

Tree work was started today along the front entrance. The sugar maples lining the driveway are being removed because of their extensive rot and decay. All of these trees have lived well past their life expectancy and growing environment. They posed a safety hazard to all entering and exiting the property. It is unfortunate for their removal, however it was something which needed to be addressed. We will begin adding new plantings along the driveway starting this spring.

Monday, March 5, 2012

Lifts installed in GMC

Work continues to progress in the Grounds Management Center. Drywall is almost complete, painting has started and equipment has begun to be installed. Today two lifts were installed in the maintenance area.

Tuesday, February 21, 2012

12 Irrigation Project

The staff just finished installing our irrigation main connecting the 13th hole to 10, 11, and 12. The original main line ran through what is know the grounds management center. The piping will allow us to keep the necessary water pressure to feed this end of the golf course.

Friday, February 10, 2012

EMC Construction

Today the interior walls of the Environmental Management Center were being erected. Once completed we will have finished areas for washing off equipment, refueling, and mixing/storing of chemicals and fertilizers.

Thursday, February 2, 2012

Pouring 2nd Floor

The 2nd deck (equipment storage) is being poured today along with the floor of the EMC building (mix and load area). An estimated 7 concrete trucks will be needed to complete the pour. By tomorrow the floor should be strong enough to walk on. It will reach full strength in 7 days.

Monday, January 30, 2012

Drywall

The drywall and fire ceilings are being installed throughout the administration area. The shop and storage areas walls will be constructed out of plywood. All of the electric and plumbing is mostly complete throughout the adminstration section.

Friday, January 13, 2012

Snow

Well our first snowfall of the year was not a huge amount. We received about an inch yesterday before it changed over to rain. What ever snow remains will be here for at least a little while due to the frigid temps over the weekend.

Wednesday, January 11, 2012

Material Storage Bins

The material or bulk storage bins were located this week. The blocks pictured to the left will make up the walls on the outside and insides of each bay. The base will be a concrete pad which we are hoping to pour next week. This bins will allow us to store topdressing, mulch, and gravel in large volumes on site.

Monday, January 9, 2012

2nd Deck

This is a view from inside the 2nd level of equipment storage. The floor is the last component to be finished along with utilities. The floor will be comprised of 3.5 inches of concrete. Once the heat is installed throughout the building; the contractor will pour the floor.

Friday, December 23, 2011

Happy Holidays

The Grounds Management Department would like to wish everyone a wonderful holiday season and a Happy New Year! We will see everyone in 2012!!

Gas Tap

The gas company has made the connection for gas service to both buildings. This will allow us to temporally heat the building in order to finish pouring concrete on the second level and begin the drywall. The plumbing and electric will begin next week.

Wednesday, December 21, 2011

Framing

Framing is almost complete on all levels of the GMC. Drywall will begin after the 1st of the year.

Saturday, December 10, 2011

GMC Floor


On Friday, the floor or slab for the GMC building was poured. The crews worked all day and into the evening to get the slab poured and leveled out. An estimated 14 concrete truck loads was needed. The floor takes a few days to set up before framing can begin.