The drywall and fire ceilings are being installed throughout the administration area. The shop and storage areas walls will be constructed out of plywood. All of the electric and plumbing is mostly complete throughout the adminstration section.
Monday, January 30, 2012
Friday, January 13, 2012
Snow
Wednesday, January 11, 2012
Material Storage Bins
The material or bulk storage bins were located this week. The blocks pictured to the left will make up the walls on the outside and insides of each bay. The base will be a concrete pad which we are hoping to pour next week. This bins will allow us to store topdressing, mulch, and gravel in large volumes on site.